# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 17: Pre-construction plans and documentation

Extent: E+W+S

(1) Each programme, statement, plan, protocol, scheme or details required to be approved under Condition 16 must be submitted for approval at least 4 months before the intended commencement of construction, except where otherwise stated or unless otherwise agreed in writing by the MMO.
(2) The licensed activities must be carried out in accordance with the programmes, statements, plans, protocols, schemes and details approved under Condition 16.

---