# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 25: Aids to navigation

Extent: E+W+S

The undertaker must during the whole period of the construction, operation, alteration, replacement or decommissioning of the authorised scheme exhibit such lights, marks, sounds, signals and other aids to navigation, and take such other steps for the prevention of danger to navigation, as directed by Trinity House.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/9/paragraph/25 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-9/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.