# The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015, Paragraph 7


Within Work No. 1B, the wind turbine generator foundations must not have—
(a) a total seabed footprint exceeding 1,005,300 square metres;
(b) subsea scour protection exceeding 1,084,850 cubic metres in total volume of material;
(c) subsea scour protection exceeding 755,400 square metres in total seabed footprint.

---
Source: https://www.legislation.gov.uk/uksi/2015/1592/schedule/9/paragraph/7 (the official version)
Page: https://openlegislation.uk/dogger-bank-teesside-a-and-b-offshore-wind-farm-order-2015/schedule-9/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.