# The Domestic Renewable Heat Incentive Scheme Regulations 2014, Regulation 14: Metering requirements

Extent: E+W+S

(1) The requirements referred to in regulation 3(d) are that, in relation to all eligible meters used in relation to the plant , other than any eligible electricity meters installed in order to comply with the requirements specified in regulation 5(2)—
(a) the requirements set out in paragraph (2) are met (“the metering requirements”); or
(b) the metering requirements in paragraph (2)(a) are met and the Authority is satisfied that, were the plant given accreditation, no participant or NRI would, as a consequence of the failure to meet the other metering requirements, be entitled to receive RHI payments which are materially greater than would be the case were all the metering requirements met.
(2) The requirements referred to in paragraph (1)(a) are that—
(a) in the case of a meter installed—
(i) before the relevant date, a certified installer was responsible for installing it or for checking that it was properly installed;
(ii) on or after the relevant date, a certified installer was responsible for installing it;
(b) each eligible meter—
(i) is positioned in accordance with the requirements specified in regulation 15 if the plant is a biomass plant or regulation 16 if the plant is a heat pump;
(ii) is properly calibrated;
(iii) is properly installed and in good working order; and
(iv) bears a label which identifies the meter using a unique reference number which enables the meter to be consistently identified when the information recorded by the meter is submitted to the Authority.

---
Source: https://www.legislation.gov.uk/uksi/2014/928/regulation/14 (the official version)
Page: https://openlegislation.uk/domestic-renewable-heat-incentive-scheme-regulations-2014/regulation-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.