# The Domestic Renewable Heat Incentive Scheme Regulations 2014, Regulation 27: Calculation of RHI payments where metering is not required

Extent: E+W+S

Subject to regulation 48(6)(b), where the Authority has not provided a metering statement for an accredited domestic plant, the RHI payment for that plant for any quarterly period is calculated in accordance with the following formula—
(A×B4)−Cwhere—
(a)A is the applicable initial tariff or subsequent tariff for the accredited domestic plant;
(b)B is the deemed annual heat generation for the plant; and
(c)C is the grant funding deduction for the accredited domestic plant for the quarterly period.

---
Source: https://www.legislation.gov.uk/uksi/2014/928/regulation/27 (the official version)
Page: https://openlegislation.uk/domestic-renewable-heat-incentive-scheme-regulations-2014/regulation-27
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.