# The Domestic Renewable Heat Incentive Scheme Regulations (Northern Ireland) 2014, Regulation 54: Scheme review and evaluation


(1) The Department must keep the operation of the domestic RHI scheme under review.
(2) The Department may select an accredited domestic plant for monitoring for the purpose of that review (“evaluation monitoring”).
(3) Where the Department makes a decision to select an accredited domestic plant for evaluation monitoring—
(a) the Department must write to the participant who owns the accredited domestic plant to advise that it has been selected for evaluation monitoring; and
(b) the Department may request entry at any reasonable hour to—
(i) inspect the accredited domestic plant;
(ii) install any measuring instruments and related equipment (“metering equipment”) which the Department may consider necessary;
(iii) inspect any metering equipment installed under this regulation;
(iv) carry out meter readings or download any information recorded by the metering equipment;
(v) check, repair or replace any metering equipment;
(c) the Department may request that the participant—
(i) assist with the maintenance of the meters or the taking of readings;
(ii) keep any records specified by the Department;
(iii) provide any information held by the participant that is required by the Department, including any information prepared by the certified installer who was responsible for the installation of the accredited domestic plant.

---
Source: https://www.legislation.gov.uk/nisr/2014/301/regulation/54 (the official version)
Page: https://openlegislation.uk/domestic-renewable-heat-incentive-scheme-regulations-northern-ireland-2014/regulation-54
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.