# The Domestic Renewable Heat Incentive Scheme Regulations (Northern Ireland) 2014, Schedule 4: Tariffs


Table 1 :
Tariff for accredited domestic plant which have received a RHPP grant
Tariff for 7 years (pence per kWh)
Air Source Heat Pumps
3.5
Biomass
5.6
Ground Source Heat Pumps
8.2
Solar Thermal
13.5
Table 2 :
Upfront payment for accredited domestic plant which have not received an RHPP grant
Upfront payment (£)
Air Source Heat Pumps
1700
Biomass
2500
Ground Source Heat Pumps
3500
Solar Thermal
320

---