Schedule 2 SALMONELLA CONTROL PROGRAMMES (ZOONOSES): FEES
Table 1
Fees payable by the person in charge of a flock from which an official control sample is taken, processed and examined for the purposes of Regulation (EC) 2160/2003
| Column 1 Activity | Column 2 Fee (£) for activities commenced before 1 July 2023 | Column 3 Fee (£) for activities commenced on or after 1 July 2023 | Column 4 Fee (£) for activities commenced on or after 1 July 2024 |
|---|---|---|---|
| Time spent travelling to and from premises (in this Table “travelling time”) for the purposes of obtaining an official control sample (in addition to any other fees specified) | 14 per quarter hour or part quarter hour spent, up to a maximum of 84 | 12 per quarter hour or part quarter hour spent, up to a maximum of 72 | 12 per quarter hour or part quarter hour spent, up to a maximum of 72 |
| Time (other than travelling time) spent obtaining an official control sample for examination in a laboratory (in this Table “the time fee”) where specified in addition to the fee for that activity in columns 2, 3 or 4 | 9 per quarter hour or part quarter hour spent | 12 per quarter hour or part quarter hour spent | 12 per quarter hour or part quarter hour spent |
| Taking an official control sample from a flock of laying hens | 32 plus the time fee | 41 plus the time fee | 49 plus the time fee |
| Taking an official control sample from a chicken or turkey breeding flock | 52 plus the time fee | 68 plus the time fee | 83 plus the time fee |
| Taking an official control sample from a chicken broiler or turkey fattening flock | 72 plus the time fee | 95 plus the time fee | 117 plus the time fee |
| Examination of an official control sample in a laboratory | 14 per sample examined | 18 per sample examined | 21 per sample examined |
Table 2
Fees payable by the operator of a laboratory in relation to an approval under Article 12 of Regulation (EC) 2160/2003
| Column 1 Activity | Column 2 Fee (£) for applications received before 1 July 2023 | Column 3 Fee (£) for activities received on or after 1 July 2023 | Column 4 Fee (£) for applications received on or after 1 July 2024 | |
|---|---|---|---|---|
| Processing an application for an initial laboratory approval or a biennial renewal of a laboratory approval | 73 | 86 | 86 | |
| Conducting inspections for quality assurance | Number of tests for which the laboratory is approved: | 688 | 1,025 | |
| one test | 350 | |||
| two tests | 361 | |||
| three tests | 372 | |||
| four tests | 384 | |||
| Conducting collaborative testing required to obtain and maintain approvals as a testing laboratory for salmonella | 34 per test | 44 per test | 44 per test | |
Table 3
Fees payable by the person in charge of a flock for conducting tests under point 4 (b) of Part D of Annex 2 to Regulation (EC) 2160/2003
| Column 1 Activity | Column 2 Fee (£) for activities commenced before 1 July 2023 | Column 3 Fee (£) for activities commenced on or after 1 July 2023 | Column 4 Fee (£) for activities commenced on or after 1 July 2024 |
|---|---|---|---|
| Conducting tests on seven dust and faecal samples taken from each flock | 99 | 123 | 146 |
| Conducting bacteriological sampling and testing of the caeca and oviducts of 300 birds in each flock | 2,470 | 3,203 | 3,936 |
| Conducting bacteriological sampling and testing of the shell and the content of 4,000 eggs of each flock | 3,080 | 3,517 | 3,954 |