In article 64(2)—

(a)

in the definition of “relevant proposals”—

(i)

in paragraph (b) after “impediments” insert “including a timetable for doing so”;

(ii)

in paragraph (c), for the words from “four months” to the end substitute “the response period”;

(b)

at the end insert—

  • ““response period” means—

    1. (a)

      in a case described in point (b) of Article 17.3 of the recovery and resolution directive, two weeks beginning with the date on which the institution received the notice; and

    2. (b)

      in any other case, four months beginning with that date.”.