Regulation 2 Interpretation
In these Regulations—
-
“air source heat pump” means a plantf1 which generates heat using a thermodynamic cycle by transferring energy stored in the form of heat in the ambient air outside a property and uses that energy to heat a liquid;
-
“boiler upgrade grant” means the grant, the value of which has been published under regulation 13(1) or (4), which is payable by the Authorityf2 to an installer under these Regulations in relation to the installation of—
- (a)
an air source heat pump,
- (b)
a ground source heat pump, or
- (c)
a biomass boiler;
- (a)
-
“boiler upgrade voucher” has the meaning given in regulation 15(1);
-
“biomass boiler” means a plant which—
- (a)
is designed and installed to burn solid biomassf3 to provide heat,
- (b)
is designed to minimise direct heat loss to the immediate area in which it is installed,
- (c)
is not capable of providing heat to a property without using a liquid to deliver that heat, and
- (d)
is not designed to generate heat for the purpose of cooking food;
- (a)
-
“building” means a roofed construction having walls, for which energy is used to condition the indoor climate, and reference to a building includes reference to a building unit in that building;
-
“building unit” means a section, floor or apartment within a building which is designed or altered to be used separately;
-
“commencement date” means the day on which these Regulations come into force;
-
“commissioned”, in relation to a plant, means the completion of such procedures and tests as constitute, at the time they are undertaken, the usual industry standards and practices for that type of plant which demonstrate that it is capable of operating and generating heat;
-
“connected person”, in relation to an installer, means any person connected to them within the meaning of section 1122 of the Corporation Tax Act 2010f4;
-
“consumer code” means a code of practice approved by the Chartered Trading Standards Institutef5;
-
“eligible plant” has the meaning given in regulation 8;
-
“eligible property” has the meaning given in regulation 5;
-
“energy performance certificate” has the meaning given in regulation 2(1) of the EPB Regulations;
-
“the EPB Regulations” means the Energy Performance of Buildings (England and Wales) Regulations 2012f6;
-
“financial year” means—
- (a)
the period beginning with the commencement date and ending with 31st March 2023, or
- (b)
any subsequent 12 month period beginning with 1st April and ending with the following 31st March;
- (a)
-
“grant application” has the meaning given in regulation 14(1);
-
“grant change notice” has the meaning given in regulation 13(4);
-
“ground source heat pump” means a plant which generates heat using a thermodynamic cycle by transferring energy stored in the form of heat from the ground, including water in the ground or surface water or both, and uses that energy to heat a liquid;
-
“heat pump” means a plant which is an air source heat pump or a ground source heat pump but not both;
-
“installer” means a person who is certified by the Microgeneration Certification Schemef7 or a scheme—
- (a)
which is equivalent to the Microgeneration Certification Scheme, and
- (b)
under which installers are certified to standards equivalent to the Microgeneration Certification Scheme’s standards by a certification body or organisation accredited by UKAS to the standard approved by the Secretary of State under regulation 4(1)(a);
- (a)
-
“installer obligation” means an obligation specified in regulation 17;
-
“mains gas” means a supply of the kind mentioned in section 5(1)(b) of the Gas Act 1986f8;
-
“NOx” means oxides of nitrogen;
-
“original heating system” has the meaning given in regulation 5(1)(c)(ii);
-
“PM” means particulate matter;
-
“properly made”—
- (a)
in the case of a grant application, means an application which provides the information required by regulation 14(3), and in relation to which any information specified in a notice issued in accordance with regulation 14(4) or (5) has been received by the Authority,
- (b)
in relation to a redemption application, means an application which provides the information required by regulation 16(3), and in relation to which any information required by a notice issued in accordance with regulation 16(4) has been received by the Authority;
- (a)
-
“quarter” means a period of three months beginning with 1st January, 1st April, 1st July, or 1st October;
-
“recommendation report” has the meaning given in regulation 4(1) of the EPB Regulations;
-
“redemption application” has the meaning given in regulation 16(1);
-
“related property”, in relation to an eligible property, or property to which regulation 14(1)(b) applies, means any building or swimming pool which is used by, or available for the use of, an owner or occupier of that property and where the building, building unit or swimming pool is not covered by the valid energy performance certificate for that property;
-
“relevant installation standard” has the meaning given in paragraph 2 of Schedule 4;
-
“relevant financial year” means a financial year beginning with—
- (a)
the commencement date,
- (b)
1st April 2023, or
- (c)
1st April 2024;
- (a)
-
“the Scheme” has the meaning given in regulation 3;
-
“UKAS” means the United Kingdom Accreditation Service, a company limited by guarantee and incorporated in England and Wales under number 3076190;
-
“urban area” means an area classified as urban in the “2011 rural-urban classification of output areas” published by the Office for National Statistics in August 2013f9.
For the purposes of these Regulations, an energy performance certificate for a property is “valid” if—
it was entered on the register required to be maintained under regulation 27(1) of the EPB Regulations no more than 10 years before the date on which it is relied on for the purposes of a grant application in relation to that property, and
no other energy performance certificate for the property has since been entered on the register.
Where there is more than one owner of a property, then any reference in these Regulations to the owner of the property includes any person who is an owner of the property.
For the purposes of these Regulations, a scheme is equivalent to the Microgeneration Certification Scheme if it is approved as equivalent by the Secretary of State.
For the purposes of these Regulations, a property does not cease to be “fuelled by mains gas” if the supply meter point in relation to the property is capped or clamped, where “supply meter point” has the meaning given in the Uniform Network Code (as defined in section 36C(7) of the Gas Act 1986)f10.
Annotations
Footnotes
- f1
-
And see section 100(3) of the 2008 Act for the definition of “plant”.
- f2
-
And see section 100(3) of the 2008 Act for the definition of “Authority”.
- f3
-
And see section 100(3) of the 2008 Act for the definition of “biomass”.
- f4
- f5
-
The Chartered Trading Standards Institute is a Royal Charter company registered in England and Wales with company no. RC000879.
- f6
-
S.I. 2012/3118, as amended by S.I. 2013/10, 181 and 603, 2014/880, 2015/609 and 1681, 2016/284 and 888, 2017/368, 2018/362, 2020/1422, and 2021/370 and 439.
- f7
-
Details of the scheme are available at www.mscertified.com.
- f8
-
1986 c. 44. Section 5 was substituted by section 3 of the Gas Act 1995, and sub-section (1)(b) was amended by S.I. 2012/2400.
- f9
-
ISBN 978 0 580 78472 9. This international standard was published by the British Standards Institution on 31st October 2012; which defines an urban area as one with a population of 10,000 people or more.
- f10
-
Section 36C(7) was inserted by section 81(1) of the Energy Act 2011 (c. 16). See paragraph A4.1.1 of the Transportation Principal Document of the Uniform Network Code, issued on 24th July 2020, for the definition of “supply meter point”. Copies of that document are available at www.gasgovernance.co.uk/TPD. Hard copies are not available.