The information is—

(a)

the unique reference number under which the eligible plant is certified under the Microgeneration Certification Scheme or an equivalent scheme (see paragraph 1(a) and (b) of Schedule 4),

(b)

the unique identifier of the boiler upgrade voucher,

(c)

the name of the manufacturer, the model, and the serial number of the eligible plant installed for the eligible property or property to which regulation 14(1)(b) applies,

(d)

where the eligible plant installed was a biomass boiler, the biomass emissions certificate,

(e)

where regulation 14(1)(b) applies (property not eligible at the time of the grant application), the unique reference number for the valid energy performance certificate for the regulation 14(1)(b) property which complies with regulation 16(2), and

(f)

such other information as the Authority may require to enable it to determine the redemption application.