Regulation 33 Provision of commencement of building work information by the regulator

Original text. Later amendments are not shown.

(1)

If the regulator receives a commencement notice which includes information required under regulation 9(3A)(a) or (b) or 17(3A)(a) or (b) of the HRB Regulations, the regulator must—

(a)

give a copy of the notice to the collecting authority, and

(b)

if the regulator gives, in relation to the commencement notice, a rejection notice under regulation 9(4) or regulation 17(4) of the HRB Regulations, notify the collecting authority that the rejection notice has been given.

(2)

If the regulator receives a commencement notice which includes information required under regulation 16(3CA)(a) or (b) of the 2010 Regulationsf1, the regulator must—

(a)

give a copy of the notice to the collecting authority, and

(b)

if the regulator gives, in relation to the commencement notice, a rejection notice under regulation 16(3E) of the 2010 Regulationsf2, notify the collecting authority that the rejection notice has been given.

(3)

The regulator must give the copy of the commencement notice, required under paragraph (1)(a) or (2)(a), before the end of the period of 10 working days beginning with the day on which the commencement notice is received.

(4)

The regulator must give the notification, required under paragraph (1)(b) or (2)(b), before the end of the period of 5 working days beginning with the day on which the regulator gives the rejection notice.

(5)

If rejection of a commencement notice referred to in paragraph (1) or (2) is appealed and the regulator is notified that the appeal is allowed, the regulator must notify the collecting authority that the appeal has been allowed before the end of the period of 5 working days beginning with the day on which the regulator receives the appeal decision.

Annotations

Footnotes

f1

Regulation 16(3CA) is inserted by regulation 28 of this instrument.

f2

Regulation 16(3E) was inserted by S.I. 2023/911.