(1)

Each of the following is a “building control application”—

(a)

an application for building control approval with full plans;

(b)

an initial notice;

(c)

a higher-risk building application;

(d)

an updated application.

(2)

A building control application is “made”—

(a)

in the case of an application for building control approval with full plans, if the application is given, in accordance with regulation 14 of the 2010 Regulationsf1—

(i)

to a local authority, or

(ii)

if the application is a section 91ZB application, to the regulator;

(b)

in the case of an initial notice, if the notice is given to a local authority in accordance with section 47(1)(a) of the 1984 Act;

(c)

in the case of a higher-risk building application, if the application is submitted to the regulator in accordance with regulations 3(a) and 4, or 11(1)(a) and 12, of the HRB Regulations;

(d)

in the case of an updated application, in the circumstances described in regulation 42(3).