# The Building Safety Levy (England) Regulations 2025, Regulation 62: Amendment of HRB Regulations: rejecting completion certificate applications


(1) The HRB Regulations are amended as follows.
(2) In regulation 44 (completion certificate applications: decisions), after paragraph (2) insert—
“(2A) Where the completion certificate application was required by regulation 40(1)(g) to include a levy liability statement, the regulator must reject the application unless a notice under regulation 63(4) of the BSL Regulations which states that the collecting authority agrees with the levy liability statement has been received from the collecting authority or, where there is more than one authority, such a notice has been received from each collecting authority.”.
(3) In regulation 45 (partial completion certificates), after paragraph (11) insert—
“(11A) Where the partial completion certificate application was required by paragraph (2)(j) to include a levy liability statement, the regulator must reject the application unless a notice under regulation 63(4) of the BSL Regulations which states that the collecting authority agrees with the levy liability statement has been received from the collecting authority or, where there is more than one authority, such a notice has been received from each collecting authority.”.

---
Source: https://www.legislation.gov.uk/ukdsi/2025/9780348273779/regulation/62 (the official version)
Page: https://openlegislation.uk/draft-building-safety-levy-england-regulations-2025/regulation-62
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.