OpenLegislation

Regulation 40 Delay after completion of allocation processes

Original text. Later amendments are not shown.

(1)

Where the delay period has expired—

(a)

a proceed notice or a proceed direction must not be given; and

(b)

the delivery body must not re-run part only of the allocation process.

(2)

Where paragraph (1) applies the delivery body must—

(a)

re-run the allocation process;

(b)

comply with regulation 34(2) to (6); and

(c)

after completion of the re-run, comply with regulation 35 and Chapter 4 of this Part.

(3)

In this regulation, “delay period” means—

(a)

where a variation notice was not required to be given when the allocation process commenced, a period of more than 5 months has expired since the application closing date; or

(b)

where a variation notice was required to be given when the allocation process commenced, a period of more than 5 months has expired since the date on which the variation notice was required to be given.

(4)

The allocation framework for the allocation round may provide for a period other than “5 months” stated in paragraph (3)(a) or (b) and where such other period is provided, “delay period” has effect with that modification.