Regulation 9 Data reconciliation of interim rate payments
This regulation applies where, before the conclusion of a quarterly obligation period, the BSCCo carries out a relevant allocation run in respect of a day in that period and the reconciled interim rate amount in relation to that day for an electricity supplier is different to the net levied interim rate payment for that supplier.
Where that reconciled interim rate amount is more than the net levied interim rate payment the supplier must pay the difference to the CFD counterparty.
Where that reconciled interim rate amount is less than the net levied interim rate payment the CFD counterparty must pay the difference to the supplier.
The CFD counterparty must make a payment it is required to make by virtue of paragraph (3) by the 8th working day after the day on which the BSCCo carried out the relevant allocation run following which the CFD counterparty is required to make that payment.
Where a supplier fails to pay all or part of a payment it is required to make by virtue of paragraph (2) that supplier must pay the CFD counterparty simple interest at the rate specified in regulation 35(1) on any unpaid amount from the day after the 5th working day after the day referred to in paragraph (5).
For the purposes of this regulation—
the reconciled interim rate amount for a supplier in relation to a day is equal to the amount of electricity supplied by that supplier on that day multiplied by the interim levy rate which applies to that day by virtue of regulation 8(3);
the net levied interim rate payment for a supplier in relation to a day is the sum of the interim rate payment that supplier was required to pay in respect of that day and any payments that supplier was previously required to pay in respect of that day by virtue of paragraph (2), less any payments the CFD counterparty was previously required to pay to that supplier in respect of that day by virtue of paragraph (3);
a relevant allocation run is an Initial Volume Allocation Run or a Reconciliation Volume Allocation Run; and
the amount of electricity supplied by an electricity supplier on a particular day is the amount of electricity which the BSCCo determines, on the basis of the most recent relevant allocation run in relation to that day, as the amount of electricity supplied by that supplier on that day.