Regulation 20 Amendment to regulation 14A (temporary site exclusions and exemption certificates)

Original text. Later amendments are not shown.

In regulation 14A—

(a)

in paragraph (1)(b)(i) for the words “13 months” to the end substitute “the date determined in accordance with the CFD as the Milestone Delivery Date”;

(b)

for paragraph (2) substitute—

“(2)

Subject to paragraphs (4) and (5), an eligible generator may not make an application in respect of a CFD unit in the next allocation round if the site of the main generating structures of the CFD unit is the same as, or includes any part of, an excluded site; and in this paragraph, “next allocation round” means the first allocation round in which the eligible generator could otherwise have made such an application after the allocation round further to which the CFD notification in respect of the CFD referred to in paragraph (1) was given.”.