# The CRC Energy Efficiency Scheme Order 2010, Article 31: Electricity generating credit


(1) In article 30, “electricity generating credit” applies where—
(a) an applicant generates electricity;
(b) the applicant is not issued with a ROC and is not in receipt of a financial incentive made by virtue of section 41 of the Energy Act 2008 in respect of that generation;
(c) the generation does not occur at a place described in paragraph (3); and
(d) the electricity generated is supplied to a public body or undertaking and that supply is a supply of electricity under paragraph 1 or 6 of Schedule 1, such electricity being “the generated and supplied electricity”.
(2) Electricity generating credit is the amount of emissions calculated in accordance with paragraph 29 of Schedule 1 in respect of the generated and supplied electricity.
(3) The places referred to in paragraph (1) are—
(a) an EU ETS installation where electricity is generated;
(b) a nuclear power station;
(c) a hydro-generating station which was ineligible for a ROC.
(4) In paragraph (3), “hydro-generating station” has the meaning given by article 2(1) of the Renewables Obligation Order 2009 and as if that article applied to Scotland and Northern Ireland.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/article/31 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/article-31
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.