# The CRC Energy Efficiency Scheme Order 2010, Article 62: Information on half hourly meters and amount of supplies


(1) This article applies to a public body or undertaking (“A”) which—
(a) during a qualifying year of a phase is supplied with electricity measured by a settled half hourly meter; and
(b) is not required to register, or is not a member of a group required to register, as a participant.
(2) For the purposes of paragraph (1), A is supplied with electricity where that supply is made in accordance with sections 1 to 3 of Schedule 1.
(3) A must provide to the administrator in respect of the qualifying year of a phase the information described in paragraph (4) and do so in respect of—
(a) the first phase, on or before 30th September 2010; and
(b) the second and subsequent phases, within 6 months of the beginning of the phase.
(4) The information referred to in paragraph (3) is—
(a) the information in paragraph 2 of Schedule 5, as applicable to A;
(b) a list of the settled half hourly meters which measure the supply of electricity to A and the identification numbers of those meters; and
(c) in respect of the supply of electricity to A measured by settled half hourly meters and non-settled half hourly meters—
(i) whether or not the supply equalled or exceeded 3000 MWh and, if it did, the amount of the supply; and
(ii) if the supply exceeded 6000 MWh, why A is not required to register as a participant and which deductions, if any, under section 4 or 5 of Schedule 1 apply.
(5) Unless otherwise agreed by the administrator, the information must be provided using the Registry.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/article/62 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/article-62
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.