# The CRC Energy Efficiency Scheme Order 2010, Paragraph 1: Electricity


(1) Subject to section 3, a public body or undertaking (“A”) is supplied with electricity by a person (“B”) where—
(a) A agrees with B that B will supply electricity to A and that A will pay B for that supply;
(b) A receives a supply further to that agreement; and
(c) that supply is measured by a metering device or is a dynamic supply.
(2) A supply of electricity is made at the time it is received.
(3) In sub-paragraph (1)(c) “metering device” is a device where the electricity supplied is charged for as measured by the device.

---