# The CRC Energy Efficiency Scheme Order 2010, Paragraph 20: Un-metered transport supply: electricity


(1) Sub-paragraph (2) applies where—
(a) A has consumed a supply of electricity for the purposes of transport; and
(b) part of that supply so consumed was not measured by a meter of any sort (“un-metered electricity transport supply”).
(2) Where this sub-paragraph applies, A may decide that un-metered electricity transport supply is not consumed for the purposes of transport.
(3) A decision made under sub-paragraph (2)—
(a) may be made in respect of—
(i) qualifying electricity in the qualification year of a phase and where so made, applies also to supplies of electricity during the phase;
(ii) a phase where it was not made in respect of the qualification year, where such a decision is made on or before the participant submits its footprint report;
(b) must not be altered during the phase.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/schedule/1/paragraph/20 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/schedule-1/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.