# The CRC Energy Efficiency Scheme Order 2010, Paragraph 1: Core electricity supplies


A core supply of electricity means a supply to which sections 1 to 3 of Schedule 1 apply where the supply is—
(a) measured by the following type of meter—
(i) a settled half hourly meter;
(ii) a non-settled half hourly meter, where paragraph 3 is satisfied; or
(iii) a non-domestic meter;
or
(b) a dynamic supply.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.