# The CRC Energy Efficiency Scheme Order 2010, Paragraph 6: Core gas supplies


(1) A core supply of gas means a supply to which sections 1 to 3 of Schedule 1 apply measured by a meter which is—
(a) a daily meter;
(b) an hourly meter; or
(c) a large gas point meter.
(2) A meter under sub-paragraph (1) includes any ancillary device used in connection with that meter which allows the amount of the supply measured by that meter to be read.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/schedule/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/schedule-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.