# The CRC Energy Efficiency Scheme Order 2010, Paragraph 12: Significant group undertakings transferring to another participant


(1) Sub-paragraphs (2) to (5) apply where the following change occurs—
(a) a participant (“G”) consists of a group;
(b) a significant group undertaking (“H”) which was a member of G becomes a significant group undertaking as a member of another participant (“J”).
(2) In respect of the change—
(a) G and J must notify the administrator of the change and when it occurred;
(b) in the notification of J, J must inform the administrator whether or not J requests that H may apply for registration as a separate participant; and
(c) if such a request is made, H may make an application to be a participant and if it does, must do so in accordance with article 11.
(3) Where H is registered as a participant separate from J, H must comply with Part 4 as if H had been a participant for the whole of the year in which the change occurs.
(4) Where H is not registered as a separate participant, H is treated as if it was a significant group undertaking as a member of J for the whole of the year in which the change occurs.
(5) Where the change occurs in an annual reporting year and—
(a) G has a residual measurement list, G must amend its residual measurement list to exclude any residual supplies of H;
(b) subject to sub-paragraph (6), where H is not registered as a separate participant and—
(i) where—
(aa) J does not have a residual measurement list; and
(bb) G has a residual measurement list including residual supplies of H,
J must compile a residual measurement list from those residual supplies of H;
(ii) where J has a residual measurement list, J must amend its list to include the residual supplies of H.
(6) Sub-paragraph (5)(b) does not apply where—
(a) H is not registered as a separate participant; and
(b) G has a group CCA exemption or had a member CCA exemption in respect of H.
(7) Where G has a group CCA exemption or had a member CCA exemption in respect of H, J has a member CCA exemption in respect of H.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/schedule/6/part/3/crossheading/footprint-years-and-annual-reporting-years/paragraph/12 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/schedule-6/part-3/crossheading-footprint-years-and-annual-reporting-years/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.