# The CRC Energy Efficiency Scheme Order 2010, Paragraph 5: Significant group undertakings transferring between groups


(1) Sub-paragraphs (2) to (4) apply to a significant group undertaking (“G”) of a group (“H”) where—
(a) G becomes a significant group undertaking as a member of another group (“J”) in the post-qualification period; and
(b) H and J are groups to which article 27(2) applies.
(2) In respect of the change H and J must—
(a) apply for registration as participants in accordance with article 11;
(b) when doing so notify the administrator of the change and when it occurred; and
(c) in the notification by J, it must inform the administrator whether or not J requests that G may apply for registration as a separate participant.
(3) Where a request is made under sub-paragraph (2)(c), that must be treated as a request under article 25(2) and paragraphs (3) to (6) of that article apply.
(4) In respect of the information required under paragraph 6 of Schedule 5—
(a) H must include the information which applied to G in the qualification year;
(b) J must not include that information.

---
Source: https://www.legislation.gov.uk/ukdsi/2010/9780111491232/schedule/6/part/3/crossheading/postqualification-period/paragraph/5 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2010/schedule-6/part-3/crossheading-postqualification-period/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.