# The CRC Energy Efficiency Scheme Order 2013, Article 27: Changes to undertakings and groups


(1) Paragraph (2) applies where—
(a) a requirement to register applies to a group or undertaking under article 24 or 25;
(b) a change described in section 1 of Part 3 of Schedule 5 applies to that group or undertaking after the qualification day but before the group or undertaking makes an application for registration in accordance with article 12 (“the post-qualification period”).
(2) Where this paragraph applies—
(a) a group or undertaking to which article 24 or 25 would otherwise apply must instead register as a participant as provided by section 1 of Part 3 of Schedule 5; and
(b) other undertakings affected by such change must comply with that section.

---
Source: https://www.legislation.gov.uk/ukdsi/2013/9780111535370/article/27 (the official version)
Page: https://openlegislation.uk/draft-crc-energy-efficiency-scheme-order-2013/article-27
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.