Paragraph 1 Electricity
Subject to sub-paragraph (3), and sections 3 and 4—
a public body or undertaking (“A”) is supplied with electricity where—
A agrees with a person (“B”) that B will supply electricity to A;
A receives a supply further to that agreement; and
that supply is measured by a metering device or is an unmetered supply;
A is supplied with electricity received by another public body or undertaking (“C”) where—
A agrees with B that B will supply electricity to C;
C receives a supply further to that agreement; and
that supply is measured by a metering device or is an unmetered supply.
A supply of electricity is made at the time it is received.
Sub-paragraph (1) does not apply to the extent that the electricity is used directly for—
the generation, transmission or distribution of electricity; or
the transport, supply or shipping of gas.
In this paragraph,—
-
“unmetered supply” is a supply of electricity to premises which is—
- (a)
supplied otherwise than through a metering device; and
- (b)
is connected to a distribution system of an electricity distributor within the meaning of section 6 of the Electricity Act 1989f1.
- (a)
Annotations
Footnotes
- f1