# The CRC Energy Efficiency Scheme Order 2013, Paragraph 23: Un-metered transport supply: gas


(1) Sub-paragraph (2) applies where—
(a) A has consumed gas for the purposes of transport; and
(b) part of that supply so consumed was not measured by a meter of any sort (“un-metered gas transport supply”).
(2) Where this sub-paragraph applies, A may decide that un-metered gas transport supply during a phase is not consumed for the purposes of transport.
(3) A decision made under sub-paragraph (2)—
(a) may be made in respect of a phase where such a decision is made on or before the participant submits its first annual report for that phase;
(b) must not be altered during the phase.

---
Source: https://www.legislation.gov.uk/ukdsi/2013/9780111535370/schedule/1/paragraph/23 (the official version)