Subject to regulation 48(6)(b), where the Authority has not provided a metering statement for an accredited domestic plant, the RHI payment for that plant for any quarterly period is calculated in accordance with the following formula—
( A× B 4 )−C where—
(a) A is the applicable initial tariff or subsequent tariff for the accredited domestic plant;
(b) B is the deemed annual heat generation for the plant; and
(c) C is the grant funding deduction for the accredited domestic plant for the quarterly period.

---