# The Domestic Renewable Heat Incentive Scheme Regulations 2014, Regulation 53: Exceptions to duty to give registration


(1) The Authority must not give registration if paragraph (2), (3) or (4) applies.
(2) This paragraph applies if the giving of registration would cause the total cost of all metering and monitoring payments payable for—
(a) the period commencing on the relevant date and ending on 31st March 2015 to exceed £0.58 million; or
(b) the period commencing on 1st April 2015 and ending on 31st March 2016, or any subsequent period commencing on 1st April and ending on the subsequent 31st March, to exceed £2.42 million.
(3) This paragraph applies if the agreement for which registration is sought relates to an accredited domestic plant for which another metering and monitoring agreement has been given registration which has not been withdrawn.
(4) This paragraph applies if the Authority has advised the applicant that further information is required before registration can be given and that information is not provided within 12 weeks of the date on which it was last requested.
(5) Where the Authority does not give registration it must notify the applicant that the registration application has been rejected, giving reasons.

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111111192/regulation/53 (the official version)
Page: https://openlegislation.uk/draft-domestic-renewable-heat-incentive-scheme-regulations-2014/regulation-53
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.