# The Domestic Renewable Heat Incentive Scheme Regulations 2014, Regulation 54: Changes affecting registration


Once the Authority becomes aware that a participant has transferred to another person (“a new owner”) ownership of all or part of the accredited domestic plant to which a registered metering and monitoring agreement relates, no metering and monitoring payment may be made until—
(a) the new owner has notified the Authority under regulation 48(2)(a);
(b) the Authority has taken the steps set out in regulation 48(5);
(c) if the Authority requests that the new owner provide further information about the metering and monitoring agreement, that information has been provided;
(d) if the Authority decides to review the registration, the Authority is satisfied that—
(i) the metering and monitoring agreement continues to meet the requirements specified in Schedule 7; and
(ii) the terms of the metering and monitoring agreement are being complied with; and
(e) the Authority has updated the central register and notified the new owner of this.

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111111192/regulation/54 (the official version)
Page: https://openlegislation.uk/draft-domestic-renewable-heat-incentive-scheme-regulations-2014/regulation-54
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.