# The Domestic Renewable Heat Incentive Scheme Regulations 2014, Regulation 7: Installation requirements


The requirements referred to in regulation 3(b) are that, on the RHI date for the plant, all parts of the plant have the same first commissioning date and that date is on or after 15th July 2009.

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111111192/regulation/7 (the official version)
Page: https://openlegislation.uk/draft-domestic-renewable-heat-incentive-scheme-regulations-2014/regulation-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.