Paragraph 2
The information referred to in paragraph 1(b) is—
the name and address of the testing laboratory by which tests have been carried out;
the name and signature of the person authorised by the testing laboratory to issue the certificate;
the date of issue of the certificate together with a certificate reference number;
the date of the accreditation of the testing laboratory to EN ISO/IEC 17025:2005 and the accreditation number;
the name, model, manufacturer and installation capacity of the plant tested;
the date of the testing;
confirmation that—
emissions of NOx and PM have been tested on the same occasion;
the testing was in accordance with the requirements set out in paragraph 3 or 4; and
the test was carried out at no less than 85% of the installation capacity of the plant;
confirmation that when tested as specified in sub-paragraph (g)—
emissions of PM from the plant did not exceed 30 grams of PM per gigajoule net heat input; and
emissions of NOx did not exceed 150 grams of NOx per gigajoule net heat input;
the actual emissions of PM and NOx measured when the plant was tested as specified in sub-paragraph (g);
a list of—
the types of fuel used during the testing; and
the types of fuel which can be used so as to ensure that the emission limits referred to in sub-paragraph (h) are not exceeded;
the moisture content of the fuel used during testing and the maximum moisture content which can be used so as to ensure that the emission limits referred to in sub-paragraph (h) are not exceeded;
a statement indicating whether or not the plant tested was a manually stoked natural draught plant;
a list of plants, other than the plant tested, in the type-testing range of plants for the certificate, if any.