The model conforms to paragraph 9 of Schedule 19 (automatic power-down in displays other than televisions) where—

(a)

the model is tested for—

(i)

each end user selectable signal input interface type which has specified that it can carry power management control signals or data; or

(ii)

if there are two or more identical signal interfaces not labelled for a specific host product type, one of these signal interfaces is selected at random for testing;

(b)

if there are labelled or menu designated signal interfaces (such as a computer, set top box or analogous) the appropriate host signal source device is connected to the designated signal interface for the test; and

(c)

no signal by any input source is detected and the model switches into standby mode, off mode or networked standby mode.