# The Electricity and Gas (Community Energy Saving Programme) Order 2009, Article 16: Notifications


(1) An action which a generator or supplier intends to be a qualifying action must be notified to the Authority within one month of the action being commenced.
(2) A notification must—
(a) include a written confirmation from a local authority in whose area any qualifying actions will be promoted that it has been consulted on the qualifying actions which a generator or a supplier intends to promote in its area;
(b) include sufficient information to show how the generator or supplier intends the action to be a qualifying action.

---
Source: https://www.legislation.gov.uk/ukdsi/2009/9780111481929/article/16 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-community-energy-saving-programme-order-2009/article-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.