# The Electricity and Gas (Energy Companies Obligation) Order 2012, Article 10: Determining obligations for a supplier who is a member of a group


Where this article applies, in respect of each of the obligations referred to in article 8(2), the supplier’s obligation for a phase is—
J×( H K ) where—
“J” is the amount produced by applying the formula set out in article 9 where—
(a) A and T have the same meaning as in that article;
(b) Tx is the amount of electricity or gas supplied in the relevant notification period by the group to which the supplier belongs as determined in accordance with article 11;
“H” is the amount of electricity or gas notified by a supplier for the relevant notification period;
“K” is the amount of electricity or gas supplied in the relevant notification period by the group to which the supplier belongs.

---
Source: https://www.legislation.gov.uk/ukdsi/2012/9780111530276/article/10 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-companies-obligation-order-2012/article-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.