# The Electricity and Gas (Energy Companies Obligation) Order 2012, Article 6: Overall obligation period


(1) The overall obligation period is the period—
(a) beginning with 1st January 2013, except for a new supplier; and
(b) ending with 31st March 2015.
(2) For a new supplier the overall obligation period begins with, as applicable, 1st April 2013 or 1st April 2014.

---