OpenLegislation

Article 9 Determining obligations for a supplier who is not a member of a group

Original text. Later amendments are not shown.

Where this article applies, in respect of each of the obligations referred to in article 8(2), the supplier’s obligation for a phase is—

( A 2 )( Tx T )

where—

  • “A” is the value given for the obligation in the following table in relation to the phase;

    Carbon emissions reduction obligation

    Carbon saving community obligation

    Home heating cost reduction obligation

    Phase 14.18MtCO21.36MtCO2£0.84bn
    Phase 28.36MtCO22.72MtCO2£1.68bn
    Phase 38.36MtCO22.72MtCO2£1.68bn
  • “Tx” is the amount of electricity or gas supplied in the relevant notification period by the supplier as determined in accordance with article 11;

  • “T” is the total amount of electricity or gas, as applicable, supplied in the relevant notification period by all suppliers as determined in accordance with article 11 but excluding those suppliers for whom an obligation of zero applies under article 8(6) and (7).