Article 10 Determining supply
For the purposes of articles 8 and 9, the amount of electricity or gas supplied by a supplier or group in the relevant notification period is—
where the amount notified under article 6 for that period is more than a qualifying supply but less than the amount in sub-paragraph (b)(i) or (ii) (as the case may be), the amount determined using the formula in paragraph (2);
where the amount notified under article 6 for that period is equal to or more than—
800 gigawatt hours of electricity; or
4000 gigawatt hours of gas,
the notified amount.
The formula referred to in paragraph (1)(a) is—
where—
- (a)
“A” is the amount of electricity or gas notified by the supplier or group for the relevant notification period;
- (b)
“B” is—
- (i)
in the case of an electricity supplier, 400 gigawatt hours; or
- (ii)
in the case of a gas supplier, 2000 gigawatt hours.
- (i)