# The Electricity and Gas (Energy Company Obligation) Order 2014, Article 8: Determining obligations for a supplier who is not a member of a group


Where this article applies, in respect of each of the obligations referred to in article 7(1) and the provisional solid wall minimum requirement referred to in article 7(2), the supplier’s obligation or requirement, as applicable, for a phase is—
A×Tx T where—
(a) “A” is half of the value given for the obligation or requirement in the following table in relation to the phase;
Carbon emissions reduction obligation
Carbon saving community obligation
Home heating cost reduction obligation
Provisional solid wall minimum requirement
Phase 1
6.2MtCO2
3MtCO2
£1.85bn
2MtCO2
Phase 2
6.2MtCO2
3MtCO2
£1.85bn
2MtCO2
(b) “Tx” is the amount of electricity or gas supplied in the relevant notification period by the supplier as determined in accordance with article 10;
(c) “T” is the total amount of electricity or gas, as applicable, supplied in the relevant notification period by all suppliers as determined in accordance with article 10 but excluding those suppliers for whom an obligation of zero applies under article 7(6) and (7).

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111122297/article/8 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2014/article-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.