# The Electricity and Gas (Energy Company Obligation) Order 2014, Article 9: Determining obligations for a supplier who is a member of a group


Where this article applies, in respect of each of the obligations referred to in article 7(1) and the provisional solid wall minimum requirement referred to in article 7(2), the supplier’s obligation or requirement, as applicable, for a phase is—
J×( H K ) where—
(a) “J” is the amount produced by applying the formula set out in article 8 where—
(i) A and T have the same meaning as in that article;
(ii) Tx is the amount of electricity or gas supplied in the relevant notification period by the group to which the supplier belongs as determined in accordance with article 10;
(b) “H” is the amount of electricity or gas notified by a supplier for the relevant notification period;
(c) “K” is the amount of electricity or gas supplied in the relevant notification period by the group to which the supplier belongs.

---
Source: https://www.legislation.gov.uk/ukdsi/2014/9780111122297/article/9 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2014/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.