OpenLegislation

Article 24 Notification requirements for completed measures

Original text. Later amendments are not shown.

(1)

A measure is notified to the Administrator in accordance with this article if the notification—

(a)

is made, in writing, by the participant that promoted the measure;

(b)

includes a calculation of the score for the measure;

(c)

if the measure is a demonstration action, includes—

(i)

the total cost in pounds sterling incurred by the participant in promoting and monitoring the demonstration action (“the actual cost”);

(ii)

a breakdown of the actual cost;

(iii)

the information obtained by the participant as to whether the demonstration action achieved cost savings; and

(iv)

an assessment of the effectiveness of the demonstration action at achieving cost savings;

(d)

includes such other information relating to the measure as the Administrator may require;

(e)

is made after the measure is completed; and

(f)

is made on time within the meaning of article 25.

(2)

The Administrator must publish, on its website, a summary of the information provided by a participant in respect of a demonstration action under paragraph (1)(c).

(3)

For the purposes of this Order, a measure is completed—

(a)

in the case of a demonstration action, when the planned monitoring of the demonstration action is completed;

(b)

in any other case, when the installation of the measure is completed.

(4)

In this article, “planned monitoring” means the arrangements for monitoring whether a demonstration action achieves cost savings—

(a)

as described in the application for approval of the demonstration action in accordance with article 20(2)(a)(iii); or

(b)

as otherwise agreed, in writing, by the Administrator.