Article 35 Transfer of obligations
A participant may apply to the Administrator with another participant for all or part of its total home-heating cost reduction obligation or total solid wall minimum requirement to be transferred from the participant (“A”) to the other participant (“B”) (“a proposed transfer”).
An application under paragraph (1) must—
be made by A and B, in writing, on or before 30th September 2021;
state in respect of which one of the following the application is being made (“the relevant obligation”)—
a total home-heating cost reduction obligation; or
a total solid wall minimum requirement;
state the amount of its relevant obligation that A intends to transfer to B (“the proposed transfer amount”); and
include such other information relating to the proposed transfer as the Administrator may require.
The Administrator must not approve the application if—
the proposed transfer amount exceeds A’s relevant obligation;
approval of the application would result in A or B’s total solid wall minimum requirement being greater than its total home-heating cost reduction obligation;
having regard to section 30O of the Gas Act 1986f1 and section 27O of the Electricity Act 1989f2 (maximum amount of penalty or compensation), the Administrator considers that, if the application were approved, there is a significant risk that it would adversely affect the Administrator’s ability to enforce the requirements placed on B under this Order; or
where A and B are not members of the same group, the Administrator considers that, if the application were approved, there is a significant risk that B will be unable to achieve its total home-heating cost reduction obligation or total solid wall minimum requirement.
If the Administrator decides not to approve the application it must in writing—
notify A of any reasons for that decision relating to A; and
notify B of any reasons for that decision relating to B.
If the Administrator approves the application—
A’s relevant obligation is treated as reduced by the proposed transfer amount, and the Administrator must notify A in writing of its reduced relevant obligation; and
B’s relevant obligation is treated as increased by the proposed transfer amount, and the Administrator must notify B in writing of its increased relevant obligation.
Annotations
Footnotes
- f1
-
1986 c.44. Section 30O was inserted by paragraph 1 of Schedule 14 to the Energy Act 2013 (c.32).
- f2
-
1989 c.29. Section 27O was inserted by paragraph 2 of Schedule 14 to the Energy Act 2013.