# The Electricity and Gas (Energy Company Obligation) Order 2018, Paragraph 3


The condition in this paragraph is that—
(a) a pre-installation EPC expresses the energy performance rating of the premises as band F or G; and
(b) an owner or occupier of the premises has confirmed in writing that, to the best of its knowledge and belief, no changes were made to the premises, after the pre-installation EPC was issued and before the qualifying action was installed, which would increase the energy performance rating of the premises to band A, B, C, D or E.

---
Source: https://www.legislation.gov.uk/ukdsi/2018/9780111171769/schedule/4/paragraph/3 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2018/schedule-4/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.