A measure meets the condition in this article if—
(a) the measure is installed as part of an ECO4 project at social housing for which the pre-project SAP band is band D; and
(b) the measure is—
(i) an innovation measure; or
(ii) an insulation measure installed in order to meet the minimum insulation requirement in article 24 or 25 in relation to a heating measure falling within sub-paragraph (i).

---