# The Electricity and Gas (Energy Company Obligation) Order 2022, Article 43: Notification requirements for completed measures


A measure is notified to the Administrator in accordance with this article if the notification—
(a) is made, in writing, by the participant that promoted the measure;
(b) is made after the measure is completed;
(c) is made on time within the meaning of article 44; and
(d) includes such other information relating to the measure as the Administrator may require.

---