# The Electricity and Gas (Energy Company Obligation) Order 2022, Article 48: Calculation of data light measure, exempted project, heating repair and heating replacement allowances


(1) The Administrator must calculate a participant’s data light measure allowance, exempted project allowance, heating repair allowance and heating replacement allowance in accordance with the following formula—
(Ht / £224.3 million) x A, with the result expressed as the nearest integer, rounding 0.5 up to the next integer.
(2) In paragraph (1)—
(a) “A” is the value given for the allowance in the following table—
Allowance
Value
Data light measure allowance
5,000 data light measures.
Exempted project allowance
7,500 ECO4 projects.
Heating repair allowance
20,000 ECO3 interim delivery actions or ECO4 projects.
Heating replacement allowance
20,000 surplus actions, ECO3 interim delivery actions or ECO4 projects.
(b) “Ht” is the participant’s total home-heating cost reduction obligation.

---
Source: https://www.legislation.gov.uk/ukdsi/2022/9780348236606/article/48 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2022/article-48
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.