{
  "url": "https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2022/article-63",
  "json_url": "https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2022/article-63.json",
  "legislation": "ukdsi/2022/9780348236606",
  "legislation_title": "The Electricity and Gas (Energy Company Obligation) Order 2022",
  "legislation_url": "https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2022",
  "path": "article/63",
  "kind": "article",
  "number": "63",
  "heading": "Determination whether building fabric repair allowance is exhausted",
  "text": "(1) This article applies for the purposes of article 61.\n(2) A participant’s building fabric repair allowance is exhausted only if X is equal to or greater than the participant’s building fabric repair allowance, where “X” is the sum of—\n(a) the building fabric repair increases for the ECO4 projects promoted by the participant for which the Administrator has given a score under article 47(1)(b) before the ECO4 project in question;\n(b) the building fabric repair increases for the qualifying actions promoted by the participant for which the Administrator has given a score under article 47(1)(c)(i) before the ECO4 project in question.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/ukdsi/2022/9780348236606/article/63",
    "retrieved_at": "2026-10-30T14:45:17.688479+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}