# The Electricity and Gas (Energy Company Obligation) Order 2022, Article 82: Final determination and reporting


(1) The Administrator must determine whether a participant has—
(a) achieved its total home-heating cost reduction obligation;
(b) met its total solid wall minimum requirement; and
(c) met its total EFG minimum requirement.
(2) The Administrator must notify the participant in writing of its determination under paragraph (1) before 1st October 2026.
(3) The Administrator must submit to the Secretary of State a report each month setting out the progress which participants have made towards achieving their total home-heating cost reduction obligation.
(4) The Administrator must submit—
(a) its first report under paragraph (3) in the month following the month in which the commencement date occurs; and
(b) its final report under paragraph (3) in April 2026.
(5) Before 1st October 2026, the Administrator must submit to the Secretary of State a report setting out whether participants achieved the overall home-heating cost reduction target.

---
Source: https://www.legislation.gov.uk/ukdsi/2022/9780348236606/article/82 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2022/article-82
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.