# The Electricity and Gas (Energy Company Obligation) Order 2023, Article 11: ECO4A qualifying actions: general requirements


(1) A measure meets the requirements of this article if the measure—
(a) is an insulation measure or a heating control measure;
(b) is installed at domestic premises;
(c) results in the reduction in the cost of heating those premises to 21 degrees Celsius in the main living areas and 18 degrees Celsius in all other areas;
(d) is completed on or after 30th March 2023 and before 1st April 2026;
(e) is installed at—
(i) premises erected before 1st April 2022; or
(ii) premises which were first occupied as domestic premises before the day on which the installation is completed;
(f) is not funded by a grant made by—
(i) a public authority; or
(ii) any person distributing funds on behalf of a public authority; and
(g) is not a measure notified to the Administrator in accordance with article 43 of the 2022 Order.

---
Source: https://www.legislation.gov.uk/ukdsi/2023/9780348248340/article/11 (the official version)
Page: https://openlegislation.uk/draft-electricity-and-gas-energy-company-obligation-order-2023/article-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.